일위대가 방식과 작업조 방식의 생산성 분석 및 비교 연구

Metadata Downloads
Alternative Title
Productivity Analysis on the Standard Quantity-Per-Unit Costing Method and Work Crew Combination Method
Abstract
Recently, the non-vibration mass excavation method is used on sewage pipes and road construction sites in Jeju. However, a construction cost estimation based on the unit quantity does not provide a proper unit price that doesn't consider about the size of construction site, regional differences and construction period. In this study, it analyzes the productivity by comparing the standard quantity-per-unit costing method that based on the standard quantity per unit and the work crew combination method which using the data related the amount of labor and works.
It is based on the site monitoring of the non-vibration mass excavation method that is used in construction sites near Jeju. For this, data of 35 sites were collected: a regression equation was derived from the 30 data, and verification was carried out through the remaining 5 data. The analysis concluded that a day's workload is 16.43㎥.
In addition, a combination of the equipment considering the site conditions and the amount of labor, which varies with the number of work crew was obtained in order to estimate the construction cost of the work crew combination method. The construction cost was calculated based on the one-day workload (16.43㎥) derived from the regression analysis.
The cost then was analyzed and compared with the standard quantity-per-unit costing method.
The model of Standard Quantity-Per-Unit Costing Method and Work Crew Combination Method from this research will present a new direction for Vibration-free Rock Excavation which had problems and limited options by selecting the standard of each estimation method and determining best combination of the equipment as well as appropriate amount of labor on the following conditions of the construction site.
Moreover, it will be used not only as a beneficial basic data for those similar construction methods but also a data in order to analyze the efficient productivity for the Work Crew Combination Method in some civil construction projects.
Author(s)
조홍준
Issued Date
2011
Awarded Date
2011. 8
Type
Dissertation
URI
http://dcoll.jejunu.ac.kr/jsp/common/DcLoOrgPer.jsp?sItemId=000000005473
Alternative Author(s)
Cho, Hong-Jun
Affiliation
제주대학교
Department
대학원 토목해양공학과
Advisor
이동욱
Table Of Contents
목 차 ⅰ
표 목 차 ⅲ
그림 목차 ⅳ
Summary ⅴ
I. 서 론 1
1.1 연구 배경 및 목적 1
1) 연구 배경 1
2) 연구 목적 2
1.2 연구 범위와 방법 3
1) 연구 범위 및 절차 3

II. 작업조 적산방식에 관한 기존 연구 동향 6

III. 이론 및 고찰 8
3.1 일위대가 8
1) 표준품셈 8
2) 표준품셈에 의한 예정가격 산정방식 10
3.2 작업조 방식에 따른 공사비 산정 11
1) 작업조 방식에 따른 공사비 산정 11
2) 작업조 방식의 공사비 산정 사례 - 미국의 사례 12
3.3 표준품셈의 일위대가 방식과 작업조 방식 14
1) 일위대가 기반 표준품셈의 고찰 14
2) 작업조 기반 표준품셈의 고찰 15

IV. 무진동 암 터파기 공법에 대한 공사비 분석 16
4.1 무진동 암 터파기 공법의 유사공법 16
1) 무진동 할암 공법 16
2) 미진동 파쇄기 공법 16
4.2 무진동 암 터파기 공법의 작업절차 17
4.3 무진동 암 터파기 공법의 생산성 분석 19
1) 데이터 수집 방법 19
2) 무진동 암 터파기 공법의 Cycle 분석 20
3) 일위대가 방식과 작업조 방식의 적산과정 비교 및 분석 23
4) 일위대가 방식에 따른 공사비 도출 27
5) 작업조 방식에 따른 공사비 도출 29
(1) 회귀분석의 개념 29
(2) 비정상적 관측치 32
(3) 회귀분석을 통한 작업조 방식의 회귀식 개발 35
(4) 회귀방정식의 검증 38
4.4 일위대가 방식과 작업조 방식의 공사비 비교 39
1) 일위대가 방식과 작업조 방식의 총공사비 비교 39
2) 세부작업별 공사비 비교 41

V. 결론 44

VI. REFERENCES 46

감사의 글 49
Degree
Master
Publisher
제주대학교 대학원
Citation
조홍준. (2011). 일위대가 방식과 작업조 방식의 생산성 분석 및 비교 연구
Appears in Collections:
General Graduate School > Civil and Ocean Engineering
공개 및 라이선스
  • 공개 구분공개
파일 목록

Items in Repository are protected by copyright, with all rights reserved, unless otherwise indicated.