陸上風力 認許可 問題點 및 改善方案에 대한 考察

Metadata Downloads
Abstract
Wind power business has restrictions on locating even though it impacts its nation's economy. While the accumulated capacity of world wind power generation reach 283GW, Korea has only 0.17% of it. This stagnant of korean wind power business is because it takes long time on initial developing phase to searching for the suitable locations which has enough wind speed, and there are many restrictions in licensing due to complex procedures and regulations until the installation.

In order to invigorate wind power business in Korea, it should be licensed through the land development authorization procedure which is simpler way than others. In case of the site over 30,000㎡ in mountain, it is difficult to negotiate with Korea Porest Service through the land development authorization procedure. Even if the site is under 30,000㎡, we can not get permission for building driveway to the wind power site through the city management plan authorization process not the land development authorization procedure. 「The Guidelines for Environmental Influence Evaluation of On-shore Wind turbine (Plan)」 which Ministry of Environment is working out covers many contents that restrict wind turbine installation such as adopting index of changes in geographical features, limitation of length of wind farm, rules of separation distance between sites, and strict instructions for environmental impact study, etc.

This study analyzes those issues and suggests ideas for revising relative laws and the guideline for environmental influence evaluation in order to promote the growth of wind power business in Korea. It is considered reasonable to extend using period in the Management of Mountainous Districts Act to 20 years, allow the land development authorization procedure if the site in under 200,000㎡, and revising 「The Guidelines for Environmental Influence Evaluation of On-shore Wind turbine (Plan)」. The index of changes in geographical features should be revised or eliminated since it is not suitable for wind farm in mountains. Regarding regions for the major evaluating area, it is necessary to follow standards which already applied in other regulations. Environmental impact study for animals and plants is considered to be eliminated or limited for the environmental influence evaluation business which of generation capacity is more than 100MW. Limitation of length and rules of separation distance between wind farms are unsuitable for geography of Korea. The assessment committee of on-shore wind turbine developing business is not necessary since similar committee is exists. Also environmental site consulting regulation should be revised so that we can consult in necessity.
Author(s)
강경택
Issued Date
2014
Awarded Date
2014. 8
Type
Dissertation
URI
http://dcoll.jejunu.ac.kr/jsp/common/DcLoOrgPer.jsp?sItemId=000000006722
Department
산업대학원 풍력공학과
Table Of Contents
Ⅰ. 서 론 1
Ⅱ. 풍력건설 인허가 절차
1. 인허가 기본 절차 3
1) 인허가 방향 선택 4
2) 산지사용허가 5
2. 환경영향평가
1) 환경영향평가 구분 6
2) 자연환경보전법 및 백두대간 보호에 관한 법률 7
Ⅲ. 육상풍력 인허가 문제점
1. 육상풍력 인허가 계류현황 및 정부 규제개선 경위 9
2. 산림청 인허가 문제점
1) 산지사용허가 면적 12
2) 산지사용허가 기간 16
3. 육상풍력 환경성평가 지침(안)
1) 지형변화지수 17
2) 중점평가항목 적용대상지역 19
3) 사업단지 길이제한 20
Ⅳ. 육상풍력 인허가 개선방안
1. 관련 법령 개정
1) 신에너지 및 재생에너지 개발·이용·보급 촉진법 21
2) 산지관리법 22
2. 육상풍력 개발사업 환경성평가 지침 개선
1) 지형변화지수 25
2) 중점평가항목 적용대상지역 26
3) 사업단지 길이제한 27
Ⅴ. 결 론 28
참고문헌 30
Degree
Master
Publisher
제주대학교 산업대학원
Citation
강경택. (2014). 陸上風力 認許可 問題點 및 改善方案에 대한 考察
Appears in Collections:
Graduate School of Industry > Wind Energy Engineering
공개 및 라이선스
  • 공개 구분공개
파일 목록

Items in Repository are protected by copyright, with all rights reserved, unless otherwise indicated.